Pipeline → Build

Construction ops

Tri-Valley Logistics · GC McLarney Construction · Pacific Western (construction)

Budget

$0.0M
0approved at close

Forecast at completion

$0.0M
+2current projection

Variance

$0K
+1over budget

Next draw

$0.0M
0Draw #5 · May 2026

Cost to completion

62% complete
CategoryOriginalCommittedForecastVariance
Hard Cost$21,700,000$21,440,000$22,030,000$330,000
Sitework & utilities$4,200,000$4,200,000$4,310,000$110,000
Shell & structure$13,600,000$13,600,000$13,820,000$220,000
MEP & fire$3,900,000$3,640,000$3,900,000$0
Soft Cost$2,270,000$2,270,000$2,300,000$30,000
A&E + consultants$1,550,000$1,550,000$1,580,000$30,000
Permits & fees$720,000$720,000$720,000$0
GC Fee$2,350,000$2,350,000$2,390,000$40,000
General conditions + fee$2,350,000$2,350,000$2,390,000$40,000
Contingency$1,470,000$0$1,270,000−$200,000
Construction contingency$1,470,000$0$1,270,000−$200,000
Owner Cost$1,610,000$1,180,000$1,870,000$260,000
Owner reserves & FF&E$1,610,000$1,180,000$1,870,000$260,000
Total development cost$29,400,000$27,240,000$29,860,000$460,000

Draw schedule

4 of 7 funded
  • Draw #1Sep 2025
    $4.10MFunded
  • Draw #2Nov 2025
    $5.30MFunded
  • Draw #3Jan 2026
    $4.90MFunded
  • Draw #4Mar 2026
    $3.70MFunded
  • Draw #5May 2026
    $2.95MSubmitted
  • Draw #6Jul 2026
    $3.40MPending Lender
  • Draw #7Sep 2026
    $2.90MPlanned